A proposed 580-megawatt solar energy development near Haswell could generate an estimated $56 million in property tax revenue over 35 years, provide millions of dollars annually to participating landowners and support hundreds of construction-related jobs, according to information provided to the Kiowa County Independent by renewable energy developer Ørsted.

The proposed Haswell Solar project would occupy just over 4,000 acres of privately owned land near Haswell, with construction potentially beginning in early 2028 and commercial operations targeted for early 2030.

The project reached another step in the local permitting process Monday, Nov. 2, when Kiowa County received a revised 1041 permit application from the developer.

According to the Kiowa County Board of County Commissioners (BOCC) office, the county has 28 days to determine whether the revised application is complete. If determined complete, the county will have approximately 120 days to reach a decision. If additional information or revisions are required, a new 28-day completeness review period will begin when the developer resubmits.

The update follows a Sept. 30 public information session during which residents had an opportunity to learn about the proposed facility and raise questions about its potential impact on the community.

Charlotte Bellotte, Ørsted’s Head of Communications for Onshore External Affairs, provided written responses to questions submitted by the Independent regarding the project’s development, economic impact, construction plans, environmental considerations and long-term responsibilities.

Project Development and County Review

Ørsted is a Denmark-headquartered renewable energy company involved in the development and operation of wind, solar and energy storage projects in the United States and internationally.

According to the company, Haswell Solar would have a generating capacity of 580 megawatts and produce enough electricity annually to equal the estimated consumption of approximately 150,000 homes. The anticipated operating life is approximately 35 years.

The company did not provide an estimated number of solar panels.

Haswell Solar is progressing through Kiowa County’s 1041 permitting process, which allows Colorado local governments to regulate certain developments and activities considered matters of state interest.

The process provides county officials an opportunity to evaluate potential effects on infrastructure, land use, natural resources and other local interests before determining whether a project should be approved and under what conditions.

Ørsted previously submitted an application and has been working with county officials to address comments. The revised application received Nov. 2 is now subject to the county’s completeness review.

The company anticipates completing major permitting activities, including the 1041 Permit, Road Use Permit and key electrical interconnection studies, by late 2027.

Construction is expected to begin in early 2028, with commercial operations targeted for early 2030. Those dates remain dependent upon the necessary approvals and continued development of the project.

Economic Impact and Employment

The project’s anticipated economic impact could be substantial for Kiowa County and participating landowners.

According to Ørsted, Haswell Solar is expected to generate approximately $56 million in property tax revenue over its 35-year operating life, an average of roughly $1.6 million annually. Actual collections could vary depending on property valuations, applicable tax rates and other factors.

The company did not provide a breakdown of how the projected revenue would be distributed among county government, the school district and other applicable taxing entities.

Ørsted also estimates approximately $5.5 million annually in payments to participating landowners. At that annual level, payments would total approximately $192.5 million over 35 years, although the company did not provide a detailed payment schedule or indicate whether those amounts would remain consistent.

All land associated with the development is privately owned and would participate through lease agreements with local landowners. The company did not disclose how many landowners are involved.

Beyond taxes and lease payments, Ørsted anticipates additional economic activity through construction, employment and purchases of goods and services.

The project is expected to support approximately 550 jobs across Colorado during construction, with up to 13 permanent positions anticipated once the facility becomes operational.

The construction employment figure is statewide and does not represent a commitment to hire 550 workers from Kiowa County.

Bellotte said the company intends to make every effort to utilize local contractors, businesses and service providers. The extent of direct local employment and spending has not yet been determined.

Roads, Water and Environmental Protections

The potential effect of large-scale construction on county roads and public infrastructure remains an important consideration as Kiowa County evaluates renewable energy developments.

With more than 4,000 acres proposed for development, Haswell Solar would require transportation of equipment, materials and workers to and from the project site.

Ørsted indicated that potential impacts on roads, public services and infrastructure would be addressed through Kiowa County’s Impact Fee Nexus Study, which the company says was adopted in September 2026.

The developer also plans to enter into a Road Use Agreement with the county to help manage and mitigate construction-related impacts.

Specific construction routes, anticipated traffic volumes, financial commitments and road repair responsibilities were not provided.

Water availability and agricultural land use are also among the issues being considered.

According to Ørsted, water needed for dust mitigation during construction would be obtained from local water providers and transported to the site as necessary. Once operational, the facility is expected to require minimal water, primarily for cleaning solar panels.

The company did not identify the water providers or estimate how much water would be needed during construction.

Ørsted is also studying potential effects on agricultural land, wildlife habitat, protected species, drainage, air quality, archaeology, geological conditions and water resources.

The development team is coordinating with Colorado Parks and Wildlife, Kiowa County staff, the county agronomist and regional experts to develop measures intended to protect those resources.

One anticipated component is a Vegetation Management Plan addressing noxious weed management, revegetation with native plant species and erosion control.

The company maintains that the facility will be developed and operated in a manner compatible with surrounding land uses and environmental conditions. Specific protections will be established through the applicable permitting and approval processes.

Electrical Infrastructure and Emergency Response

Ørsted confirmed that Haswell Solar is proposed as a solar-only facility and does not currently include battery energy storage.

Electricity generated by the project would connect to the regional grid through a proposed substation and generation tie-line connecting to Public Service Company of Colorado’s May Valley-Tundra 345-kilovolt transmission system.

Key interconnection studies are expected to be completed by late 2027.

Fire safety and emergency response planning are additional considerations for the proposed facility.

Bellotte said Ørsted would train on-site personnel in fire safety, provide appropriate equipment and conduct routine inspections to identify maintenance needs and prevent potential ignition sources.

The company also works with local fire departments at its project sites to develop emergency response plans and identify training or equipment needs.

Although Ørsted indicated that training or equipment may be provided as needed, it did not identify specific funding commitments or resources designated for Kiowa County emergency responders.

Decommissioning and Financial Responsibility

With an anticipated operating life of approximately 35 years, Haswell Solar would remain part of the Kiowa County landscape for decades if approved and constructed.

Ørsted estimates that decommissioning the facility at the end of its operating life would take between 12 and 24 months.

According to Bellotte, the site would be restored in accordance with participating landowners’ agreements and applicable permit requirements.

The company also confirmed that financial assurance for decommissioning is required as part of Kiowa County’s 1041 permitting process.

Such assurance is intended to establish financial resources for the eventual removal of equipment and required restoration, reducing the risk of those costs becoming a public responsibility.

However, Ørsted did not specify the anticipated cost of decommissioning, the amount of financial assurance that would be provided or the type of financial guarantee being considered.

Those details will be important in determining how the county protects itself and local taxpayers from potential financial obligations at the end of the project’s operating life.

Community Feedback and Next Steps

During the Sept. 30 public information session, residents raised questions about the project area, solar panel construction, soil conservation, vegetation management and economic benefits.

Bellotte said the development team appreciated the opportunity to hear directly from the community.

“All the questions and comments on topics like project area, solar panel construction, soil conservation, vegetation management, and economic benefits demonstrated that residents expect responsible development, construction, and operation of Haswell Solar,” Bellotte said.

The company did not provide an attendance figure or identify specific changes resulting from the meeting.

However, Bellotte said the development team is reviewing its application materials in light of public feedback and comments received over recent months.

“We will act on anything that improves the project and our collaboration with the community,” she said.

For Kiowa County, Haswell Solar represents a potential long-term source of tax revenue, landowner income and economic activity, along with significant land use and infrastructure considerations.

The economic figures provided by Ørsted remain company projections rather than guaranteed outcomes, and the development must still complete the necessary permitting and approval processes.

The county’s immediate next step is determining whether the revised 1041 application received Nov. 2 is complete. That determination will establish whether the project can advance toward a decision by the Board of County Commissioners or whether additional revisions will be required.

As the review continues, county officials will be tasked with evaluating the proposed development and determining what conditions and protections would accompany a project expected to operate in Kiowa County for more than three decades.

Advertisements
Prairie View Farms
Weisbrod Health

Related

Five Veterans Honored with Quilts of Valor During Veterans Day Ceremonies

November 17, 2026
Five area veterans were honored for their military service during Veterans Day celebrations in Kiowa County on Nov. 11, each receiving a handmade Quilt of Valor in recognition of their service and sacrifice.

Flag Presentation Program

November 17, 2026
Monday, November 9, Kit Carson VFW Post 3411 and Auxiliary along with members from Cheyenne Wells VFW Post 9700 presented programs in the Eads and Kit Carson schools about flag history and etiquette.

Semi-Finalists Announced for Daniels Fund Scholarship Program

November 17, 2026
The Daniels Fund and Eads High School are pleased to share the names of this year’s Daniels Scholarship Program Semi-Finalists from Eads High.

Local Veterans Share Lessons of Honor, Service and Respect with Students

November 13, 2026
For the students gathered inside the Eads High School gymnasium, the American flag became more than a familiar symbol hanging in classrooms, flying above school buildings or carried during patriotic celebrations. It became a lesson in history, sacrifice and respect, taught by men and women who understand firsthand what it means to serve beneath it.

Another Friday, Another Knowledge Bowl

November 13, 2026
The Eads High School knowledge bowl team this year is the largest in the past several years with 14 members. They hit the ground running in September with their first meet at Holly, where the A team, consisting of seniors Kennedy Gyurman and Tucker Wallace along with juniors Kindel Hoffman and Landon Zimmerman, garnered their first win.